School Building Construction In Progress

Shukre Alhamdu Lillahe, work on the school building construction has been progressing as planned. Here is where we are as of today, October 20th:
  • Masonry Work: Masonry work on the walls has been completed and the masons have stopped work for the time being. The masons still need to construct parapet walls on the East and West side of the building. Those will be built after concrete has been poured on the roof. At that time, they will also construct walls around the Chiller Pad-1 behind (East) of the building.
  • Concrete Work: Today, the last concrete beam was poured with embeds for some of the steel beams. Over the next few days, they will remove the forms and do the cleanup. Once the roof is ready for concrete pouring, they will come back and pour. At that time, they will also prepare ground and pour slab for the Chiller Pad-1.
  • Steel Work: The steel company is working on the schedule for their installation crew and will soon be installing the remainder of the steel beams and steel decking. The building will be ready for them to complete installation starting next week, Inshaa Allah.
  • Plumbing: As soon as remainder of the steel decking has been installed, the plumber will install Roof Drains to carry rain water to our Retention Pond, Inshaa Allah.
  • Steel Doors: 14 sets of Hollow Metal Doors ( 3 Double and 11 Single) for the exterior walls of the building have been ordered and are expected to be delivered/installed early in December, Inshaa Allah.
  • Glass Doors and Glass Windows: We are reviewing the shop drawings for 3 sets of double Glass Doors and 11 exterior (Fixed Glass) windows. We expect to place an order for these next week and delivery/installation is expected early in December, Inshaa Allah.
Jazakum Allahu Khairun for all your support and participation. Any question, please call me at 904.629.3822.